PP_M_030 · Firm Up Planning Jobs

Production PlanningMaintenanceMANFIRM

Firm Up Planning Jobs — Maintenance facility in the Production Planning module of standard Ross ERP 8.0. Allows planning jobs to be set to Firmed status. If a planning job is not firmed before being transferred to Process Manufacturing then it will require scheduling by the PM module. If it is firmed before transfer then all the start and end dates that have produced by the planning finite scheduler will be written to the new real job. No further scheduling will need to be done.

Open PP_M_030 in the interactive Facility Explorer →

Part of Production Planning facilities · all facilities

Menu location

Master › Planning › Schedule

Program

pp_m_firm_up_jobs

Core tables · 1

SCHEDULE_RUN_DETAILS ✎

Reference & control · 2

PROCESS_SPECIFICATIONSPLANNING_JOB_OUTPUT_QTYS ✎