PM_M_048 · Changeover Process Spec
Process ManufacturingMaintenanceMANCHANGE
Changeover Process Spec — Maintenance facility in the Process Manufacturing module of standard Ross ERP 8.0. If two or more process specifications are capable of using the same machine the changeovers (i.e. setup and clear down times) may differ depending on the order in which jobs using these specs are run. This program allows a pre-defined process spec to be used to detail what machines and labor are required in going from one process spec to another. Whe n a finite schedule is run then additional jobs that specify the relevant changeover specs will be added and scheduled.
Open PM_M_048 in the interactive Facility Explorer →Part of Process Manufacturing facilities · all facilities
Menu location
Master › Manufacturing › Master › Specification